What's new

New projects of Varaks construction company in Varna,Balchik,Dobrich

Here is a selection of the recent projects of building company Varaks Ltd. with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.
Whether searching for building a house, industrial building, swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?

What's new

June 2026 25/06/2026
The construction of the structural shell of this house in Varna is progressing at an excellent pace. The team of construction company Varaks completed the formwork for the slab at level 0 and for the internal staircase. This was followed by the installation of the reinforcement for the concrete slab and staircase structure. The concrete for the slab at level 0 has been poured, with the shuttering securely braced using adjustable steel props prior to concreting, ensuring safety and precision throughout the construction process.
Waterproofing has been laid in the foundations, which protects the structure from moisture and groundwater. The process includes laying a bitumen primer for preparing the base, gas-flame laying of the first layer of bitumen waterproofing without mineral sprinkling and subsequent laying of a second protective layer of bitumen waterproofing with sprinkling.
This is followed by the installation of XPS thermal insulation (Fibran), followed by the installation of a profiled drainage membrane (Fundalin), which will protect the waterproofing and ensure effective removal of moisture from the foundations.
Once the concrete had reached the required strength, the formwork was removed.
June 2026 24/06/2026
The construction of the house in Varna is progressing according to schedule. At this stage, the formwork for the roof slab edge beam has been removed and the facade scaffolding has been assembled. The masons of building company Varaks completed the chimneys and precisely leveled and finished the masonry work. Ventilation openings have been core-drilled through the roof slab to ensure proper ventilation. Installation of the plumbing system is currently underway. The external construction works continue with the application of a cement-lime base render, leveled in preparation for the installation of stone wool insulation.
End of the works 23/06/2026
The construction of the house near Varna continued with pouring of concrete for the parking spaces. Prior to this, the construction crew carefully leveled the ground, fitted polyethylene membrane and tied the reinforcement. After the concrete was poured, the specialists from construction company Varaks finished the surface using a vibrating screed to ensure a smooth and high-quality finish.

With the completion of these activities, all construction works assigned to our company under this project were successfully finalized. This is yet another completed project that confirms Varaks’ expertise in house construction in Varna and the surrounding region.
Beginning of the works 08/06/2026
Building company Varaks began the construction of the foundations of a photovoltaic power plant near Dobrich by carrying out site layout marking. Following the surveying and staking-out works and the installation of batter boards, a mechanized excavation for the foundations was done.
Due to the excavation depth, the layout marking process was carried out in two stages. Initially, the upper excavation boundary was marked out, after which an additional layout marking was performed at the next level until the elevation specified in the project was reached.
This approach resulted in a double layout marking process, ensuring the required accuracy in the execution of the excavation works.
End of the works 27/05/2026
The first stage of the construction of this single-family house in Varna has been completed - the implementation of the rough construction. The building of the roof has been completed, including a complete wooden roof structure (joists and trusses), fit wooden boarding and fascia, fit roof deck, fit rafters and battens, fit roof tiles, sheet metal cladding of fascia, as well as the construction and plastering of a chimney. As part of the roofing activities, gutters and downpipes have been installed. To improve energy efficiency, under-roof thermal insulation of mineral wool has been laid. 
Important waterproofing works have also been completed - laying of bitumen waterproofing (smooth and with sprinkling) up to elevation 0.00, followed by fit of Fibran thermal insulation. A backfill has also been done around the building. 
With the successful completion of all activities up to Act 14, the team of building company Varaks completed another quality house construction project in Varna, proving professionalism in the rough construction, roofing works and overall residential construction.
End of the works 19/05/2026
The construction of this single-family house in Balchik is completed. All agreed construction and installation works have been completed qualitatively, professionally and within the agreed deadline by construction company Varaks. The facade works on the house have been finalized, including the application of high-quality mineral plaster for long-lasting protection and excellent appearance. The roof is fully completed, and the cladding of the fascia with sheet metal has been made as a final touch. 
The internal construction has also been completed - all floor screeds and internal plasters have been laid, the bedrooms are painted and ready for finishing works. The bathrooms are fully shaped, with a built plumbing installation, quality plastered walls and fitted linear siphons. The project is an example of quality construction of a house in Balchik, with attention to every detail.
May 2026 18/05/2026
The construction works on the house in Balchik continues with the fitting of laminate flooring in the rooms and the hallway. The second bathroom is fully finished with tiles, and a shower system, a cabinet with a sink, a toilet, a sink mixer, a mirror, lighting fixtures and bathroom accessories have been mounted. The interior doors in the house have also been mounted. The team of the construction company Varaks completed the cladding of the chimney body, which contributes to the finished and aesthetic appearance of the interior.
Progress of the works - 4 14/05/2026
The repair works of this house near Balchik are progressing at an excellent pace. The team of building company Varaks is ready with the fitting of the tiles in the kitchen area and the living room. Decorative cornices and moldings have been fitted on the walls. 
The renovation of the kitchen is also progressing successfully - after the travertine cladding is completed, the installation of a new custom-designed kitchen begins. A functional shower area with a modern linear siphon has been designed in the bathroom, and the plumbing installation is fully completed. The tiling of the walls is currently being done, which is a key stage of the overall renovation of the bathroom. 
The construction workers have also installed all the interior doors. In parallel, the external construction and renovation works on the facade continue, where supporting net and plaster are being fitted over the thermal insulation.
End of the works 20/03/2026
Building and repair works of a school in Dobrich
The construction and repair works of this school in Dobrich have been successfully completed. The walls and ceilings in the premises have been painted. A special place has been provided for an elevator-platform, ensuring an accessible environment. The electrician installed all the switches, sockets and lighting fixtures, thus completing another project of construction company Varaks with quality and on time.