What's new

New projects of Varaks construction company in Varna,Balchik,Dobrich

Here is a selection of the recent projects of building company Varaks Ltd. with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.
Whether searching for building a house, industrial building, swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?

What's new

October 2026 28/10/2026
Construction work on the luxury single-family house in the Varna area is progressing with a strong focus on workmanship quality and attention to every detail. At this stage of the project, the team at Varaks construction is applying the exterior render, bringing the building closer to its final architectural appearance, characterised by clean lines, a white façade, and anthracite window frames and downpipes.

The outdoor area surrounding the house is also taking shape step by step. The metal structure of the veranda has been installed, complementing the house’s modern design and making the outdoor space more comfortable and functional.

Alongside the façade and exterior works, interior finishing is also progressing. Ceramic wall and floor tiles have been laid in the bathrooms, in keeping with the overall modern interior design concept. Particular attention is being paid to the details, grout lines, and precise finishing of each individual area.
Progress of the works - 4 27/10/2026

Construction company Varaks continues work on a single-family house in Varna, with the project progressing towards the next stages of the interior finishing works.

The house façade has been fully completed and the scaffolding has been dismantled. The internal machine-applied plastering of the walls and ceilings has also been completed, preparing the rooms for the following construction and finishing works.

The construction team is currently laying cement screeds throughout all the interior rooms of the house, as well as on the terrace. All screeds are being carefully levelled to provide a smooth, stable and even base for the installation of the final floor coverings.

Beginning of the works 26/10/2026

During the initial phase of the project, Varaks Construction company carried out preparatory works for the construction of ramps serving the photovoltaic power plant in the Dobrich area. The work began with mechanical and manual excavation, formation of the design levels and preparation of the ground. This was followed by the installation of polyethylene sheeting and double-layer reinforcement mesh.

At this stage, the pouring of base concrete began on one of the ramps. The concrete was delivered by mixers and poured using a concrete pump, with the Varaks team carrying out the concrete placement and initial levelling.

Beginning of the works 20/10/2026
During the initial phase of the project in Targovishte, excavation and preparatory works were carried out for the construction of a total of 26 foundations - intended for transformer stations and an energy storage system. The team from Varaks construction company executed the excavations using both heavy machinery and manual labor, following precise geodetic measurements to determine exact locations and elevation levels. After that, the soil base was thoroughly compacted. Geotextile was laid down during the preparation of the foundation areas. A base layer of concrete (blinding concrete) has been partially poured, with work continuing in stages across the various foundation sites. Operations proceeded with shuttering installation for the reinforced concrete foundations. Steel reinforcement components have been delivered to the construction site and their fitting has begun.
Beginning of the works 08/10/2026

Construction work on the foundations for lightning protection masts at a photovoltaic power plant in Dobrich area began with the precise setting-out and marking of the site. Mechanical excavation was carried out for the foundations with the work commencing in stages, starting with a single foundation. Once the mechanical excavation had been completed, the construction workers manually trimmed and shaped the excavation.

The team from Varaks construction company installed two layers of geotextile along the bottom and sides of the excavation. The prefabricated steel reinforcement cage for the foundation was then delivered to site and installed. The steel reinforcement structure was subsequently positioned. The reinforcement cage was carefully lowered into the prepared excavation with the construction workers guiding and controlling its positioning.

Progress of the works 05/10/2026

The building works are ongoing on the water storage tanks for fire protection needs for the photovoltaic power plant near Dobrich. Construction company Varaks did the ground preparation, including the placement of gravel, levelling and compaction. A polyethylene membrane was then laid, followed by the construction of a reinforced concrete foundation slab with double-layer reinforcement mesh to ensure the required structural stability.

Upon completion of the preparatory and concreting works, the prefabricated tanks, each with a capacity of 32 m³, were installed. The installation was carried out with the necessary precision, in accordance with the pre-marked tank locations.

HDPE (high-density polyethylene) pipe connections were installed, including pipes, fittings, flanges and welded joints.

The tank ventilation system was also installed, including the required air vents.

The staged filling of the tanks with water using water tanker trucks has commenced as part of the commissioning process.

Subsequently, preparations were made for the construction of a concrete containment basin around the tanks, including the installation of the required formwork. Once the preparatory works were completed, the basin was concreted, followed by backfilling around the tanks with sand.

Progress of the works 29/09/2026
Construction works for the foundations of the CCTV system at the photovoltaic power plant near Dobrich are continuing, with preparations underway for the installation of the foundations.
At this stage, the pipes designated for technological openings and cable infrastructure routing were cut and levelled. The ground base was prepared through manual excavation works, including the shaping and levelling of the excavations, followed by backfilling and compaction using a vibrating plate compactor.
A sand backfill layer was installed beneath the foundations and was also carefully compacted. In parallel, the necessary cable infrastructure was built.
Following completion of the preparatory works, the workers from construction company Varaks precisely levelled the pre-cast foundation elements, ensuring the required accuracy for the subsequent installation of the CCTV system.
Progress of the works 28/09/2026
The construction of the substation serving the photovoltaic power plant near Dobrich continues. Works are being carried out on the construction of the cable basement, including formwork, reinforcement and concrete works. The strip foundations have been completed, as well as the shuttering and reinforcement of the reinforced concrete walls and ramps up to level 0. These have been concreted, with the required curing measures implemented and proper concrete vibration carried out. The construction workers installed thermal insulation on the walls of the cable basement.
The phased construction of the backfill has commenced, including spreading and compaction. As part of the construction works, concrete cable trenches have been constructed both inside and around the substation. The base preparation has been completed by placing and compacting gravel, followed by the installation of polyethylene and XPS insulation beneath the concrete base of the cable trenches. The concrete bases and walls of the trenches have been cast.
Installation of the substation's steel structure has commenced.
At this stage, thermal insulation works on the walls are also ongoing, together with the installation of water supply and drainage pipes.
Construction company Varaks completed the gravel backfill inside the substation.
Progress of the works - 2 21/09/2026

Construction workс on the residential building in Kavarna are progressing at a steady pace. The team at Varaks Construction is carrying out the internal refurbishment of the building, including masonry works to create functional areas within the premises and optimise the layout of the internal spaces.

As part of the current stage of the works, new PVC window frames have been installed, contributing to improved thermal insulation, energy efficiency and overall comfort within the building. Particular attention is being paid to the precise finishing and sealing of the areas around the newly installed windows and the completed masonry.

As the construction works progress, the spaces are gradually taking on their new appearance and are being prepared for the interior finishing works.

August 2026 01/09/2026

Building company Varaks continues the construction of the house in Varna. The building’s steel structure has been installed on site and permanent LT sheet metal formwork for the reinforced concrete floor slab has been installed at the second level.

At the same time, the construction workers are continuing with the reinforcement and formwork for the reinforced concrete edge beams on the ground floor.

As part of the current construction stage, a reinforced concrete veranda has also been completed.