Construction company Varaks continues work on a single-family house in Varna, with the project progressing towards the next stages of the interior finishing works.
The house façade has been fully completed and the scaffolding has been dismantled. The internal machine-applied plastering of the walls and ceilings has also been completed, preparing the rooms for the following construction and finishing works.
The construction team is currently laying cement screeds throughout all the interior rooms of the house, as well as on the terrace. All screeds are being carefully levelled to provide a smooth, stable and even base for the installation of the final floor coverings.
During the initial phase of the project, Varaks Construction company carried out preparatory works for the construction of ramps serving the photovoltaic power plant in the Dobrich area. The work began with mechanical and manual excavation, formation of the design levels and preparation of the ground. This was followed by the installation of polyethylene sheeting and double-layer reinforcement mesh.
At this stage, the pouring of base concrete began on one of the ramps. The concrete was delivered by mixers and poured using a concrete pump, with the Varaks team carrying out the concrete placement and initial levelling.
Construction work on the foundations for lightning protection masts at a photovoltaic power plant in Dobrich area began with the precise setting-out and marking of the site. Mechanical excavation was carried out for the foundations with the work commencing in stages, starting with a single foundation. Once the mechanical excavation had been completed, the construction workers manually trimmed and shaped the excavation.
The team from Varaks construction company installed two layers of geotextile along the bottom and sides of the excavation. The prefabricated steel reinforcement cage for the foundation was then delivered to site and installed. The steel reinforcement structure was subsequently positioned. The reinforcement cage was carefully lowered into the prepared excavation with the construction workers guiding and controlling its positioning.
The building works are ongoing on the water storage tanks for fire protection needs for the photovoltaic power plant near Dobrich. Construction company Varaks did the ground preparation, including the placement of gravel, levelling and compaction. A polyethylene membrane was then laid, followed by the construction of a reinforced concrete foundation slab with double-layer reinforcement mesh to ensure the required structural stability.
Upon completion of the preparatory and concreting works, the prefabricated tanks, each with a capacity of 32 m³, were installed. The installation was carried out with the necessary precision, in accordance with the pre-marked tank locations.
HDPE (high-density polyethylene) pipe connections were installed, including pipes, fittings, flanges and welded joints.
The tank ventilation system was also installed, including the required air vents.
The staged filling of the tanks with water using water tanker trucks has commenced as part of the commissioning process.
Subsequently, preparations were made for the construction of a concrete containment basin around the tanks, including the installation of the required formwork. Once the preparatory works were completed, the basin was concreted, followed by backfilling around the tanks with sand.
Construction workс on the residential building in Kavarna are progressing at a steady pace. The team at Varaks Construction is carrying out the internal refurbishment of the building, including masonry works to create functional areas within the premises and optimise the layout of the internal spaces.
As part of the current stage of the works, new PVC window frames have been installed, contributing to improved thermal insulation, energy efficiency and overall comfort within the building. Particular attention is being paid to the precise finishing and sealing of the areas around the newly installed windows and the completed masonry.
As the construction works progress, the spaces are gradually taking on their new appearance and are being prepared for the interior finishing works.
Building company Varaks continues the construction of the house in Varna. The building’s steel structure has been installed on site and permanent LT sheet metal formwork for the reinforced concrete floor slab has been installed at the second level.
At the same time, the construction workers are continuing with the reinforcement and formwork for the reinforced concrete edge beams on the ground floor.
As part of the current construction stage, a reinforced concrete veranda has also been completed.