New projects of Varaks construction company in Varna,Balchik,Dobrich

Here is a selection of the recent projects of building company Varaks Ltd. with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.
Whether searching for building a house, industrial building, swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?

What's new

Progress of the works - 3 25/09/2026

Varaks Construction Company continues the building works on the house in Varna with the application of internal machine-applied plaster to the walls and ceilings. Before the plastering work began, all surfaces were carefully prepared and primed, ensuring the necessary base for a high-quality and uniform finish.

The construction workers had previously covered and protected the window frames to prevent contamination and preserve the areas that had already been completed.

The machine-applied plaster was applied to the walls and ceilings with all main surfaces and details carefully treated and levelled. Particular attention was paid to achieving even surfaces, precise corners and smooth connections between the individual elements.

September 2026 24/09/2026

Construction company Varaks and its team of qualified construction workers continue work on the construction of the detached house near Varna.

Inside the building, plasterboard is being installed on a framework throughout all rooms. The work is being done with precision and close attention to every detail, ensuring that the surfaces are properly prepared for the next stages of the interior finishing works.

At the same time, installation of the external thermal insulation system continues. The mineral wool insulation has already been installed, providing excellent thermal and acoustic insulation properties. The facade insulation boards have been precisely fitted, preparing the building for the subsequent finishing layers.

On the roof, the installation of the waterproofing membrane has been completed, including work around the boards, vertical details and penetrations. This creates a reliable roofing system that provides the building with effective protection against weather conditions and moisture.

Progress of the works - 2 21/09/2026

Construction workс on the residential building in Kavarna are progressing at a steady pace. The team at Varaks Construction is carrying out the internal refurbishment of the building, including masonry works to create functional areas within the premises and optimise the layout of the internal spaces.

As part of the current stage of the works, new PVC window frames have been installed, contributing to improved thermal insulation, energy efficiency and overall comfort within the building. Particular attention is being paid to the precise finishing and sealing of the areas around the newly installed windows and the completed masonry.

As the construction works progress, the spaces are gradually taking on their new appearance and are being prepared for the interior finishing works.

Beginning of the works 02/09/2026
Building company Varaks started the construction of the substation serving the photovoltaic power plant near Dobrich by setting out and surveying the site. The substation is a complex facility and its building began with mechanized excavation for the foundations using specialized heavy-duty construction equipment. Due to the presence of rock within the foundation area, additional rock breaking was required using a hydraulic breaker and excavator. The excavated soil and rocks were loaded and transported by dump truck.

After the completion of the mechanized excavation, the construction workers shaped the excavation manually and outlined the foundations. Formwork for the base concrete was then fitted and the required levels were established according to the different elevations specified in the design.

The base concrete was poured in stages to ensure precise compliance with the specified design elevations and construction phases. Then, the construction of the reinforced concrete foundations of the substation began.

Shuttering and reinforcement works are being carried out on site, including complex reinforcement detailing in accordance with the design requirements.
August 2026 01/09/2026

Building company Varaks continues the construction of the house in Varna. The building’s steel structure has been installed on site and permanent LT sheet metal formwork for the reinforced concrete floor slab has been installed at the second level.

At the same time, the construction workers are continuing with the reinforcement and formwork for the reinforced concrete edge beams on the ground floor.

As part of the current construction stage, a reinforced concrete veranda has also been completed.

End of the works 31/08/2026
Construction company Varaks has completed the construction of the foundations for a photovoltaic power plant near Dobrich. As part of the final stage of the building works, the construction workers removed the formwork from the reinforced concrete slab, after which they proceeded with the waterproofing of the concrete foundations.
For the application of the two-layer waterproofing, high-quality construction materials were used, including Ceresit CR90. The selected system provides reliable protection of the concrete against water and moisture penetration.
The completed foundations will provide a reliable and durable base for the transformer substations of the photovoltaic power plant, ensuring the stability of the facilities during operation and compliance with all technical and regulatory requirements.
Building company Varaks once again demonstrates that it has a team of professionals capable of successfully delivering complex projects such as this one. The company is a reliable partner that can be trusted in the field of industrial construction, thanks to its experience, quality of workmanship and high level of professionalism.
Beginning of the works 20/08/2026
The construction of the internal road within the photovoltaic power plant (PV plant) near Dobrich began with clearing and grading the terrain using an excavator. Vegetation and the topsoil layer were removed from the route. The workers of construction company Varaks cleared the area of waste and other obstacles, after which the road alignment was shaped and properly leveled. This was followed by compaction of the road base prior to laying gravel.
Beginning of the works 13/08/2026
Construction works for the foundations of the fire-fighting water tanks at the photovoltaic power plant near Dobrich began with precise setting-out of the site. The required levels are established and profile boards are installed.
Once the preparatory works have been completed, the team from construction company Varaks proceeds with the  surveying and excavation works. The work is carried out carefully, with measurements taken using a laser level. After that the mechanized excavation works begin. The excavation is done in accordance with the approved design documentation, the specified technical parameters and the requirements of the equipment manufacturer. 
End of the works 11/08/2026
The renovation and complete refurbishment of the house near Balchik have been successfully completed. Construction company Varaks carried out a major renovation and comprehensive refurbishment, transforming the old house into a cozy and functional home with an updated appearance and enhanced comfort.
The repair works included new screeds and flooring throughout the house, new wallpaper, a new kitchen and a completely renovated bathroom, as well as new interior doors. The house has also been fitted with new UPVC windows. The plumbing and electrical installations were completely replaced.
Particular attention was paid to the property's exterior. The façade was repaired, thermally insulated and painted, giving the house a fresh and finished appearance. New decorative window shutters were also installed, adding even more charm and character to the picturesque house.
New concrete steps, a ramp and a patio were constructed at the entrance, which were subsequently finished with granite tiles.
With the complete renovation, the house near Balchik acquired a completely renewed vision, combining traditional style, modern comfort and quality construction.
Beginning of the works 15/07/2026
Building company Varaks begins construction work on the foundations for video surveillance of the photovoltaic power plant near Dobrich with preliminary building of the foundations. Construction workers carefully apply oil to the formwork sheets and make the shuttering forms for the foundations. Then they install the reinforcement and in the central part of each foundation a PVC pipe Ø200 is installed, intended for a technological opening and passage of cable infrastructure. The foundation forms are ready for pouring with concrete.