Here is a selection of the recent projects of building company Varaks Ltd. with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.
Whether searching for building a house, industrial building, swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?
Building company Varaks-Stroy is continuing the works on the foundations for transformer stations and battery storage units in Targovishte. At this stage of construction, the installation of prefabricated reinforcement structures for the columns has begun. A significant portion of the work involved the fabrication, transportation and positioning of these elements. In a dedicated work area, our team prepared the necessary column reinforcement, which was subsequently installed in the designated locations within the foundations. In the meantime, the construction crew gained some new four-legged friends, who have brought a cheerful atmosphere to the site.
Construction activities proceeded with the pouring of the foundations, using concrete specified for structural elements exposed to specific moisture conditions. A two-layer waterproofing system using Ceresit CR 90 was applied, providing additional protection for the structures. Work has also begun on the formwork for the reinforced concrete columns. At the same time, the construction of the remaining foundation structures is underway, with activities organized in phases across different sections of the site.
This was followed by the concreting of the columns, which are characterized by precise execution and excellent geometry.
At this stage of construction, a large-scale foundation infrastructure is taking shape on the site, comprising numerous reinforced concrete bases and vertical structural elements essential for the future installation of the transformer stations and the energy storage system.
Construction works on the ramps for a photovoltaic power plant near Dobrich are ongoing. The team of construction company "Varaks-Stroy" has completed the formwork and installed the reinforcement for the reinforced concrete beams on both sides of the ramps. The reinforcement cages, which serve as the load-bearing foundation for the reinforced concrete ramps, have been made.
Construction activities continued with backfilling and the laying of a polyethylene membrane. Subsequently, the reinforcement framework was installed.
The construction process proceeded with the pouring of concrete for the reinforced concrete ramps. The concrete mix was delivered by mixer trucks and placed using a concrete pump, as construction workers then spread, vibrated and leveled the concrete to achieve the required surface flatness.
Construction company "Varaks-Stroy" has successfully completed the construction of foundations for a video surveillance system at a photovoltaic power plant near Dobrich.
As part of the project, our team of construction workers carried out all necessary tasks, including site preparation and excavation, reinforcement, formwork, concreting, the installation of conduits for technical cabling, as well as the precise positioning and leveling of the cast foundations.
This project is part of our operations in the field of industrial and infrastructure construction - specifically the development of photovoltaic parks and the associated infrastructure for energy facilities. With the completion of this project near Dobrich, we once again demonstrate our professionalism and expertise in executing construction works for photovoltaic power plants, as well as in building foundation structures and infrastructure for security and video surveillance systems.
Construction company Varaks continues work on a single-family house in Varna, with the project progressing towards the next stages of the interior finishing works.
The house façade has been fully completed and the scaffolding has been dismantled. The internal machine-applied plastering of the walls and ceilings has also been completed, preparing the rooms for the following construction and finishing works.
The construction team is currently laying cement screeds throughout all the interior rooms of the house, as well as on the terrace. All screeds are being carefully levelled to provide a smooth, stable and even base for the installation of the final floor coverings.
The building works are ongoing on the water storage tanks for fire protection needs for the photovoltaic power plant near Dobrich. Construction company Varaks did the ground preparation, including the placement of gravel, levelling and compaction. A polyethylene membrane was then laid, followed by the construction of a reinforced concrete foundation slab with double-layer reinforcement mesh to ensure the required structural stability.
Upon completion of the preparatory and concreting works, the prefabricated tanks, each with a capacity of 32 m³, were installed. The installation was carried out with the necessary precision, in accordance with the pre-marked tank locations.
HDPE (high-density polyethylene) pipe connections were installed, including pipes, fittings, flanges and welded joints.
The tank ventilation system was also installed, including the required air vents.
The staged filling of the tanks with water using water tanker trucks has commenced as part of the commissioning process.
Subsequently, preparations were made for the construction of a concrete containment basin around the tanks, including the installation of the required formwork. Once the preparatory works were completed, the basin was concreted, followed by backfilling around the tanks with sand.