What's new

New projects of Varaks construction company in Varna,Balchik,Dobrich

Here is a selection of the recent projects of building company Varaks Ltd. with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.
Whether searching for building a house, industrial building, swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?

What's new

July 2026 31/07/2026
Construction company Varaks continues to make steady progress on the construction of this luxury single-family home near Varna, with all building activities proceeding according to schedule.
Our electricians are currently installing electrical wiring, constructing cable routes, mounting junction boxes, preparing switch and socket outlets, installing lighting connection points and assembling the main electrical distribution board with circuit breakers and residual current devices (RCDs).
At the same time, roof thermal insulation works are continuing, ensuring excellent energy efficiency throughout the year. Installation of stone wool insulation has also begun around the chimneys, providing high fire resistance, reliable thermal insulation and long-term protection of the roof structure.
The required sand for the cement screed has already been delivered to the construction site.Once the thermal insulation was completed, it was covered with a protective polyethylene membrane, followed by the fitting of reinforcement. Drainage openings for the roof scuppers have also been prepared. After these preparatory activities, the laying of the cement screed begins.
July 2026 23/07/2026
The construction of the steel-framed house in Varna is progressing with the installation of thermal insulation (Fibran) beneath the foundation slab. The Varaks construction team has completed the reinforcement and concrete pouring of the foundation. Afterwards the concrete surface was carefully finished to achieve a smooth, level finish.
At the same time, the foundation slab for the veranda has also been completed. Before the concrete was poured, the formwork was securely braced with support beams. XPS thermal insulation and reinforcing steel were again installed, ensuring the structural strength and energy efficiency of the foundation.
With the foundation works completed, the assembly of the steel structure has begun. The steel columns, primary beams, roof frames and structural bracing have been installed. A telescopic crane is being used as the primary lifting equipment for the erection of the steel structure.
Beginning of the works 22/07/2026
Building company Varaks begins construction and installation works on the house in Kavarna by carrying out  extensive  dismantling works. These include removing plaster, removing and  demolishing brick partition walls,  dismantling wall and floor cladding and removing sanitary fixtures and equipment from the bathrooms. The construction team has also removed the doors and windows. Scaffolding has been assembled inside the building, which will serve the dismantling works on the fireplace. External scaffolding has also been installed in preparation for the removal of the Balchik limestone façade cladding.
Progress of the works 17/07/2026
Construction company Varaks continues the finishing construction and installation works on the construction of a single-family house in Varna. The project is entering its next phase with façade works, plumbing installation and electrical installation currently in progress.
Scaffolding has been assembled around the house, enabling the safe and high-quality execution of the exterior finishing works. The application of Baumit cement-lime base coat plaster has begun, providing a durable and stable base for the subsequent façade finishes. The installation of the lightning protection system has also been completed, ensuring the safety of the building.
Inside the house, work on the plumbing installation continues. Vertical plumbing stacks and water supply pipes have been installed in the sanitary areas. Electricians continue work on the electrical installation of the house. The electrical routes are being installed, power cables are being laid and distribution boxes are being fitted as part of the complete electrical system of the house.
Beginning of the works 15/07/2026
Building company Varaks begins construction work on the foundations for video surveillance of the photovoltaic power plant near Dobrich with preliminary building of the foundations. Construction workers carefully apply oil to the formwork sheets and make the shuttering forms for the foundations. Then they install the reinforcement and in the central part of each foundation a PVC pipe Ø200 is installed, intended for a technological opening and passage of cable infrastructure. The foundation forms are ready for pouring with concrete.
Progress of the works 09/07/2026
The construction of the foundations for a photovoltaic power plant near Dobrich is progressing according to plan. At this stage, the base concrete has been poured and the layout works have been completed. The formwork was installed and the reinforcement for the foundation slab was fitted, after which the concrete for it has been poured.
Subsequently, the team of construction company Varaks completed the shuttering and reinforcement of the reinforced concrete walls to an elevation of ±0.00. Pipes with diameters of Ø160 and Ø200 were pre-installed within the walls to form openings for cable routes. Upon completion of the formwork and reinforcement works, the walls were concreted.
Progress of the works - 5 07/07/2026
The renovation works on this house near Balchik are continuing with the application of mineral façade render. The plinth has been carefully protected with masking tape to prevent staining or damage during the work process.
The tiler has already completed the tile fitting and is now beginning to fit the sink, toilet and bathroom accessories. Wallpaper and decorative friezes have been fitted in the bedrooms, living room and hallway. The installation of switches and sockets is in progress.
The team of construction company "Varaks" is also working on the exterior of the house, installing wooden shutters on the windows.
End of the works 23/06/2026
The construction of the house near Varna continued with pouring of concrete for the parking spaces. Prior to this, the construction crew carefully leveled the ground, fitted polyethylene membrane and tied the reinforcement. After the concrete was poured, the specialists from construction company Varaks finished the surface using a vibrating screed to ensure a smooth and high-quality finish.

With the completion of these activities, all construction works assigned to our company under this project were successfully finalized. This is yet another completed project that confirms Varaks’ expertise in house construction in Varna and the surrounding region.
End of the works 27/05/2026
The first stage of the construction of this single-family house in Varna has been completed - the implementation of the rough construction. The building of the roof has been completed, including a complete wooden roof structure (joists and trusses), fit wooden boarding and fascia, fit roof deck, fit rafters and battens, fit roof tiles, sheet metal cladding of fascia, as well as the construction and plastering of a chimney. As part of the roofing activities, gutters and downpipes have been installed. To improve energy efficiency, under-roof thermal insulation of mineral wool has been laid. 
Important waterproofing works have also been completed - laying of bitumen waterproofing (smooth and with sprinkling) up to elevation 0.00, followed by fit of Fibran thermal insulation. A backfill has also been done around the building. 
With the successful completion of all activities up to Act 14, the team of building company Varaks completed another quality house construction project in Varna, proving professionalism in the rough construction, roofing works and overall residential construction.
End of the works 19/05/2026
The construction of this single-family house in Balchik is completed. All agreed construction and installation works have been completed qualitatively, professionally and within the agreed deadline by construction company Varaks. The facade works on the house have been finalized, including the application of high-quality mineral plaster for long-lasting protection and excellent appearance. The roof is fully completed, and the cladding of the fascia with sheet metal has been made as a final touch. 
The internal construction has also been completed - all floor screeds and internal plasters have been laid, the bedrooms are painted and ready for finishing works. The bathrooms are fully shaped, with a built plumbing installation, quality plastered walls and fitted linear siphons. The project is an example of quality construction of a house in Balchik, with attention to every detail.