Projects Gallery

Here is a selection of our recent projects with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.

Whether searching for building of a house, a swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?

What's new

April 2021 27/04/2021
The excavations for foundations begin. The earth is loaded and removed. The trench is shaped by hand. The building is outlined. Initial concrete base is poured.
April 2021 23/04/2021
The stone is fitted on the floor. Then it will  be grouted and cleaned. The thermal insulation of the house is being installed. The interior doors are fitted. We do the decorative elements around the windows. Then the facade is prepared for rendering.
Villa near Balchik Houses and Villas
April 2021 22/04/2021
The shuttering of the retaining wall is fitted. The plumbing system of the house is being installed. The concrete for the south retaining wall towards the sea is poured. Shuttering is done and concrete is poured for concrete benches. Then the formwork of the retaining wall is removed.
April 2021 21/04/2021
The downpipes are installed. The plumbing installation is being done in the house. External connections to the water and sewer system are also done. A connection is made between the water meter shaft and the house, as well as a connection between the street sewer and the house. Inside the house plasterboard is fitted in the bathrooms for built-in structures and showers. The internal plumbing installation is being completed. Then preparation for machine render is done.
March 2021 15/03/2021
The patio around the pool is prepared for the conrete - gravel has been compacted, then rebars are fitted, shuttering is also ready. Then the concrete is poured.
End of the works 22/12/2020
The cladding is ready. The shed is mounted and the new fascia is varnished and fitted.
End of the works 18/12/2020
The works on this project in Malina village is over. The bathrooms are completely renovated and equipped. Tiles and laminate flooring are laid on the underground floor. The walls of the staircase and the underground floor are primed and painted.
End of the works 10/12/2020
Then the concrete is delivered with concrete mixer and is poured. Then the workers have leveled the surface. The foundation of the printing machine is completed.
Dismantling works in Varna Renovations and Repairs
After 02/12/2020
The works start with dismantling of sinks and mixing taps. Then the aluminum profiles and lighting are unmounted. The electrical installation works are then started. The granite flooring and concrete base are then demolished.
Building WC cabins in Varna Renovations and Repairs
End of the works 30/11/2020
The works have completed. The dividing walls and doors of the cabins are installed. A boiler is mounted. Sinks and bathroom accessories are also fitted. Industrial sink is placed in the room.