Projects Gallery

Here is a selection of our recent projects with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.

Whether searching for building of a house, a swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?

What's new

Building WC cabins in Varna Renovations and Repairs
Progress of the works 26/11/2020
The walls and the ceiling are mounted. Waterproofing of walls and floors begins. Then plasterboard is mounted on a structure for a new wall. Ventilation and lighting units are fitted. The tiles works on the walls and floor are in progress. Toilet units are mounted.
November 2020 25/11/2020
The primer is applied and the fitting of the insulation on the facade begins. The electrical installation on the facade of the house is installed. The lightning protection installation is also ready. The workers shape around the windows and doors.Once the insulation is ready the house is plastered. Decorative elements are applied to the windows frames.
Beginning of the works 23/11/2020
The repair works on this site in the village of Granichar begin with cleaning the site from grass, bushes and stones. The terrain is leveled. Then the excavation works for a new plumbing and power supply begin. Then the outdoor sink is demolished and ground is leveled. The works in the cellar begin.
Villa near Balchik Houses and Villas
November 2020 17/11/2020
Excavation works for the septic tank begin. Earth is removed with excavator.
November 2020 04/11/2020
Bituminous primer is applied on the outer walls of the pool. The skimmers and the pipes are installed. The electricity and water supply of the pool are also installed. Then soil is backfilled.
November 2020 03/11/2020
The plasterboard in the shower rooms is installed. Then plaster is applied and the tiles are fitted. Bathroom accessories, sink, toilet unit, shower are also fitted. Concrete is poured in the pit with a concrete pump. We make flooring on the terraces and inside. Waterproofing and thermal insulation have been installed in the underground and ground level. Then fiber mesh is fitted and walls are plastered. Electricity and plumbing are made in the underground level. Then the workers repair and plaster around the windows and doors.
End of the works 04/09/2020
The walls of the service room are built, plastered and painted. The chapel was built and the iconostasis was placed. The tiles are fitted.