Projects Gallery

Here is a selection of our recent projects with many photographs and explanation of the building process. Keeping you updated and fully informed about the progress makes things easy to perceive and understand.

Whether searching for building of a house, a swimming pool or repair works you can find new ideas, follow the up-to date works or just explore the current projects. So, what's new?

What's new

Beginning of the works 07/04/2021
The works begin with setting out the ground tracing before the excavation works. A construction trailer is delivered. Then the shuttering is fitted. We install the reinforcement in order to prepare for pouring concrete for a storage patio on the site.
Villa near Balchik Houses and Villas
April 2021 02/04/2021
The shuttering of the retaining wall is fitted. The plumbing system of the house is being installed.
March 2021 31/03/2021
The mineral render on the facade is applied and the facade works are completed. The decorative elements are fitted on the first floor. Excavation, shuttering and concrete works have been performed for the water meter shaft.
March 2021 30/03/2021
The plaster is appiled and the tiles are fitted in the shower room. The works on the electrical and plumbing installations continues. Inside we repair and plaster around the doors and windows, and outside we prepare the scaffolding for the facade works. The frames of the doors are sanded. The concrete path outside is finished and the steps are being shaped. The basement entrance is lifted. Then the shower room is completed.
March 2021 15/03/2021
The patio around the pool is prepared for the conrete - gravel has been compacted, then rebars are fitted, shuttering is also ready. Then the concrete is poured.
End of the works 22/12/2020
The cladding is ready. The shed is mounted and the new fascia is varnished and fitted.
End of the works 18/12/2020
The works on this project in Malina village is over. The bathrooms are completely renovated and equipped. Tiles and laminate flooring are laid on the underground floor. The walls of the staircase and the underground floor are primed and painted.
End of the works 10/12/2020
Then the concrete is delivered with concrete mixer and is poured. Then the workers have leveled the surface. The foundation of the printing machine is completed.
Dismantling works in Varna Renovations and Repairs
After 02/12/2020
The works start with dismantling of sinks and mixing taps. Then the aluminum profiles and lighting are unmounted. The electrical installation works are then started. The granite flooring and concrete base are then demolished.
Building WC cabins in Varna Renovations and Repairs
End of the works 30/11/2020
The works have completed. The dividing walls and doors of the cabins are installed. A boiler is mounted. Sinks and bathroom accessories are also fitted. Industrial sink is placed in the room.