The building site is located just couple of kilometers from Balchik on the picturesque hills of villa area Belite skali. The project includes 252 sq.m. total internal area of the house. The ground floor will comprise of 2 bedrooms, 2 bathrooms, open-plan kitchen with living room and storage room. The first floor will have 4 bedrooms, 3 bathrooms and storage room.
Outdoor area will offer swimming pool with size 4m x 9,5m and additional children section to it. A good sized barbecue will host more than 12 people under the covered patio area.
Excavation works for the septic tank begin. Earth is removed with excavator.
The aluminum doors and windows are mounted. We continue making the covers of cement and mosaic on the boards of the whole villa.
The builders make covers of cement and mosaic over the boards of the whole villa.
The back fill and the vertical planning are made on the sides and behind the villa. The roof waterproofing is in progress - a deep penetrating primer is applied, then a bituminous primer, a waterproofing tape at the base of the boards and the first layer of the waterproofing are also applied. The concrete for the ramp leading from the street to the property is poured. A second layer of waterproofing is applied. Once the roof waterproofing is ready, scaffolding is assembled and prepared for laying thermal insulation on the facade. The boards of the roof will be covered with mosaic and cement mixture.
Concrete boards are being poured. The waterproofing is being installed. Heat insulation Fibran is fitted on the part of the villa which is dug in the ground. The shuttering of the boards on the first floor is prepared, after which concrete is poured. The work on the masonry continues. The drainage pipe is fitted behind the house, after which the excavation works for the retaining walls of the plot of the villa begin. Retaining walls are ready, as well as those for the fence. Two-component waterproofing has been laid on all roofs and balconies. Then 10 cm thermal insulation is applied, rebars and PVC waterproofing are laid on the roof. The 6 cm thick screeding is applied.
The brick masonry of the ground and first floor is in progress. The reinforcement on the roof slab is laid. Once it is done, the concrete is poured.
The concrete of level 0 is poured. We make formwork on walls, beams and belts at level 0. We also make the reinforecement there. We dig and model the terrain. Then the concrete is poured for the walls and beams of level 0. The conrete is vibrated and the place is cleaned. The construction of the brickwork on the ground floor is in progress. The formwork of the beams and belts on the second floor is being prepared. Then the reinforcement bars are fitted. The concrete for level +2,40 m is poured.
The shuttering for the walls, columns and stairs of level -2,40 m is ready. The rebars are being fitted. Then the concrete is poured. The base and the concrete beams of level -2,40 m are poured. The waterproof bituminous primer of level -2,40 m is laid and then 2 layers of waterproofing applied. The heat insulation is also fitted. The soil is backfilled and compacted. The shuttering and the reinforcement of the base of level 0 are ready. The drainage of the house is being installed. The sewer pipes are laid.
At this stage the workers pour the concrete for the concrete beams and the strip foundations. After pouring concrete for the floor of level -2,40 m. they grinded it. The reinforcement and formwork are prepared for the concrete beams.
We excavate foundations of the building, BBQ and the pool. The initial concrete base is poured.
The surveyors are on site putting the beams for the boundary of the house and the pool. The building site is being fenced. Then the excavation works begin.
The work begins with clearing the terrain. The old building and the garage have been knocked down. The site is cleared and leveled.