The construction works on the industrial storage for metal products in Dobrich include: measurement of the warehouse, leveling, setting out the grade, cutting asphalt pavement with a concrete cutter, demolish asphalt pavement with a drill, excavation with an excavator and removal of the rubbish by lorry, excavation by hand and forming slopes by hand, loading and transporting earth masses with wheelbarrows, making rebars and fitting rebars, pour concrete in foundations/slabs/columns.
The works on the 1st stage have been completed and after the supply of the metal structure, the works on the 2nd stage will continue with building and installation works on axis B.
Gravel is spread and then rammed. Reinforcing grid is fitted. Preparation for pouring concrete begins. First a level is determined.
The measurements are taken and reinforcement of the foundations and columns of axis C are fitted. Concrete is poured for the foundations. The concrete for the C-axis slabs has been poured and the shuttering for the wall over the slabs and columns is being made. After that, the concrete was poured by hand on the base of the reinforced-concrete columns. The shuttering is removed. The site is being prepared for excavation works.
Construction works continue with the fitting of metal planks. Concrete is then poured in foundations and vibrated. Shuttering is being made and concrete is being poured for the connecting beams. The concrete is then vibrated and reinforcement is fitted.
When working along the C-axis, the foundations are larger than the A-axis. Measurements are taken, the existing asphalt pavement is demolished, then earth is dug and leveled by hand. Then the concrete for the foundation is poured.
The building works on the storage for metalworks in Dobrich begins with measurement and setting out the grade. The building axes and building levels are determined. After that, the asphalt pavement is cut with a paver cutter. The asphalt is demolished with a drilling machine and the top layer of gravel is dug by hand. The foundation is then vibrated and initial concrete is poured. Reinforcement is fitted in foundations and columns.