Construction works of the grain warehouses in Kardam include:
- Demolition of concrete pavement 15 cm thick;
- Excavation of retaining walls;
- Supply and install of reinforcement:
- Formwork with a height of 2.50 m;
- Supply and pour concrete B-25;
- Supply and fit joints;
- Masonry with concrete blocks 15 cm;
- Disposal of construction waste.
The masonry with concrete blocks is ready and the wall is plastered from the outside. The old asphalt in front of the entrance of the grain storage is cut with concrete cutting machine for a new flooring. The flooring is demolished with a pneumatic hammer and the place is excavated with excavator. Then the terrain is leveled by hand. Gravel is laid and compacted. After that a polyethylene membrane is laid and then a rebar grid is fitted. The leveling for the concrete is done. The concrete is poured and leveled.
Concrete has been poured on part of the concrete walls in the grain warehouse and one-sided shuttering is currently being done on the inside of the warehouse only. Construction plywood is treated with shuttering oil. The reinforcement is fitted. Walls are drilled and shuttering is made. Masonry begins at a height of more than 3 m. The openings left by the one-sided formwork of the outer wall are rendered. The 3 meter high concrete wall has been poured. Pointing is made. Concrete columns and concrete belt for masonry over 3 m high are made and concrete mixed by hand is poured on over 3 m height.
Construction works on one of the warehouses in the grain base in Kardam have been completed and works are starting on the other warehouse. The old damaged render from the walls has been removed. The sheet metal on the facade is installed. The compromised, old, concrete foundation is being demolished. The brick wall has already been demolished. Concrete floor is demolished to build foundations of concrete walls with a height of 3 m. The formwork and reinforcement for the concrete walls are fitted.
The brickworks in Kardam's granaries have finished. The internal concrete intermediate wall is also completed. A one-sided shuterring was made outside of the warehouse and rebar was fit there. Concrete is now being poured.
Concrete is poured for the concrete walls. The masonry above the concrete walls is being built. The concrete is being vibrated.
The building works in the grain warehouse in Kardam start with demolition of the concrete slab. The reinforcement and other materials are supplied on the site. A massive wall between the two warehouses is demolished and the area is cleared. Concrete has been poured on the foundations for the concrete wall next to the front doors. Reinforcement for the concrete walls and formwork is being laid.