The building site is located just couple of kilometers from Balchik on the picturesque hills of villa area Belite skali. The project includes 380 sq.m. total internal area of the house. The ground floor will comprise of 2 bedrooms, 2 bathrooms, open-plan kitchen with living room and storage room. The first floor will have 5 bedrooms and 3 bathrooms.
Outdoor area will offer swimming pool with size 4m x 9,5m and additional children section to it. A good sized barbecue will host more than 12 people under the covered patio area.
The turn key building works of this luxury villa in Balchik have been completed.
The project includes rough construction works and finishing building works, building of a swimming pool and BBQ , as well as building of retaining walls and perimeter walls.
The building works near Balchik continue with fitting of granite tiles on an internal staircase. Contact primer is applied to the retaining walls outside and then stone is being glued. The skirtings in the bedrooms and the living room are fitted.
The retaining wall behind the house is completed. The air conditioners are installed. Interior doors are also installed. The flat concrete caps are being fitted on the top of the balconies' walls. Then the exterior tiles are fitted on the patio around the house, the BBQ and around the pool. The facade around the caps of the balconies is plastered. The fitting of granite tiles on the internal staircase begins. It is bordered with a decorative, golden edging. External edgings are also installed. The tiling of the outer walls of the pool continues.
The building works on the retaining wall are at their end. The fitting of the connection boxes for the lights of the swimming pool starts. After that, contact primer is laid. The pool's walls are rendered. Leveling and fitting of curbstone begins. Inside the house the staircase on the top floor is being painted. The wallpapers in two of the bedrooms and the living room are hung. Waterproofing strips are laid on pool's corners, as well as two-component waterproofing on walls. The coping stone has been fitted. Then the glueing of the glass mosaic pool tiles and the grouting begin.
The lining of the retaining wall behind the house is being done. The rooms on the second floor are being painted. The decorative elements like moldings and cornices are painted precisely with a brush. Paint for wet rooms is applied in the bathrooms. The bedrooms on the first floor are also being painted. Installation of interior doors and skirtings begins. The stone cladding of the retaining wall continues outside.
The tiles in each bathroom and in the laundry room are fitted. The laying of the primer on the retaining walls and the cladding with stone tiles begins.
Tiling begins in the bathrooms on the ground floor of the house. In the rooms, the installation of decorative moldings and cornices continues. The gutters are installed on the facade of the house. The scaffolding is dismantled.
Construction works in Balchik continue. The granite tiles have been fitted in the bedrooms and the corridor on the first floor. Flooring in the living room and kitchen is in progress. The installation of the downpipes begins. The flooring of the terraces is being fitted. The inside of the house is primed and the ceiling cornices are installed.
The facade of the villa is painted. The granite tile lining on the facade is also finished. The flooring in the bedrooms on the ground floor is finished and the flooring in all bedrooms and bathrooms on the first floor is also finished.
The work continues with the installation of waterproofing in the bathrooms on the first floor of the house near Balchik. The mortar is applied and the tiles are fitted on the first floor. The result of the perfect gluing of the tiles (faience and terracotta) is visible in the photos. The works on the wet rooms on the ground floor begins. The plasterboard is installed in the corridor on the first floor and the staircase.
The construction of this villa near Balchik continues. The two-layer plastering of the rooms on the second floor is completed, then the plaster is sanded for a perfectly smooth surface and the primer is applied. At the same time, a two-component waterproofing is applied before the screed on the terraces. The granite facade cladding is fitted and jointed. All moldings are installed on the facade. Waterproofing strips have been laid in the bathrooms and then the waterproofing is being laid, before the faience and terracotta.
The building of the villa near Balchik continues. The construction works that are currently being carried out are priming with contact primer the walls of the barbecue, installation of thermal insulation and plastering the barbecue with supporting mesh, the cladding of the facade with granite tiles continues, as well as the installation of strips and corners and plastering of the plasterboard ceilings.
The fitting of the tiles on the facade continues. The materials of the house have been delivered. The workmen from our construction company make the construction of the plasterboard. Once the frames are mounted, the mineral wool is fitted. Then the plasterboard is installed on different levels.
The primer is applied on the facade before fitting the granite tiles. Then the fitting of the tiles with high-strength adhesive begins.
The screeding in the bathrooms and the bedrooms is being laid. The outdoor screed on the patio and around the pool is also applied.
Plaster has been laid in the bedrooms. The living room and the hallways are also plastered. The machine plaster in the garage is ready.
Preparations for machine plaster begin. Workers apply anti-rust spray wherever there are metal parts such as nails, fittings, etc. Fibran insulation is prepared for the sides around the windows. The windows are covered with nylon to prevent staining and then the Fibran is installed. The plastering of the walls begins.
The villa is plastered. The workers apply the fine plaster on the ceilings of the terraces on the groubd and first floor and in front of the barbecue.
The plastering of the villa begins. Lightning protection is installed. The electrical installation in the villa is done and the plastering of the facade with fibermesh continues.
The installation of the thermal insulation of the house begins. We fitted 3cm fiber and 10cm styrofoam on top of it. The profiles are shaped. Scaffolding is installed around the whole house. The installation of the thermal insulation on the walls, ceilings, boards and fronts of the facade continues.
The shuttering of the retaining wall is fitted. The plumbing system of the house is being installed. The concrete for the south retaining wall towards the sea is poured. Shuttering is done and concrete is poured for concrete benches. Then the formwork of the retaining wall is removed.
The concrete for the patio around the swimming pool has been poured. The retaining wall and the concrete wall around the property are finished. Excavation works for the retaining wall to the southern border of the property have begun. The plumbing installation works are also in progress.
The reinforcement is installed, the shuttering is fitted and the concrete is poured for the wall towards the street, as well as for the retaining wall of the house.
The plate of the septic tank is completed. Then the area for the parking spaces and the entrance to the house is cleared. Rebars are fitted and concrete is poured.
Excavation works for the septic tank begin. Earth is removed with excavator. The shuttering of the plate of the septic tank is then done. The concrete is poured.
The aluminum doors and windows are mounted. We continue making the covers of cement and mosaic on the boards of the whole villa.
The builders make covers of cement and mosaic over the boards of the whole villa.
The back fill and the vertical planning are made on the sides and behind the villa. The roof waterproofing is in progress - a deep penetrating primer is applied, then a bituminous primer, a waterproofing tape at the base of the boards and the first layer of the waterproofing are also applied. The concrete for the ramp leading from the street to the property is poured. A second layer of waterproofing is applied. Once the roof waterproofing is ready, scaffolding is assembled and prepared for laying thermal insulation on the facade. The boards of the roof will be covered with mosaic and cement mixture.
Concrete boards are being poured. The waterproofing is being installed. Heat insulation Fibran is fitted on the part of the villa which is dug in the ground. The shuttering of the boards on the first floor is prepared, after which concrete is poured. The work on the masonry continues. The drainage pipe is fitted behind the house, after which the excavation works for the retaining walls of the plot of the villa begin. Retaining walls are ready, as well as those for the fence. Two-component waterproofing has been laid on all roofs and balconies. Then 10 cm thermal insulation is applied, rebars and PVC waterproofing are laid on the roof. The 6 cm thick screeding is applied.
The brick masonry of the ground and first floor is in progress. The reinforcement on the roof slab is laid. Once it is done, the concrete is poured.
The concrete of level 0 is poured. We make formwork on walls, beams and belts at level 0. We also make the reinforecement there. We dig and model the terrain. Then the concrete is poured for the walls and beams of level 0. The conrete is vibrated and the place is cleaned. The construction of the brickwork on the ground floor is in progress. The formwork of the beams and belts on the second floor is being prepared. Then the reinforcement bars are fitted. The concrete for level +2,40 m is poured.
The shuttering for the walls, columns and stairs of level -2,40 m is ready. The rebars are being fitted. Then the concrete is poured. The base and the concrete beams of level -2,40 m are poured. The waterproof bituminous primer of level -2,40 m is laid and then 2 layers of waterproofing applied. The heat insulation is also fitted. The soil is backfilled and compacted. The shuttering and the reinforcement of the base of level 0 are ready. The drainage of the house is being installed. The sewer pipes are laid.
At this stage the workers pour the concrete for the concrete beams and the strip foundations. After pouring concrete for the floor of level -2,40 m. they grinded it. The reinforcement and formwork are prepared for the concrete beams.
We excavate foundations of the building, BBQ and the pool. The initial concrete base is poured.
The surveyors are on site putting the beams for the boundary of the house and the pool. The building site is being fenced. Then the excavation works begin.
The work begins with clearing the terrain. The old building and the garage have been knocked down. The site is cleared and leveled.
The site in villa area Belite skali before the building of the villa started.