Building a swimming pool in Balchik.
The building of this rectangular shaped swimming pool in Balchik started in August 2020.
The size of the pool is 12 meters x 4 meters, which gives the owners plenty of space to swim in the hot summer days. The children section is also not as small itself - 2 m x 2,70 m. We left 1 meter width for the steps and here is the result.
Building company Varaks has years of experience in building swimming pools in Varna, Balchik and Kavarna areas.
Varaks Construction Ltd is proud to announce that the construction of the pool in Balchik has completed. The coping stone and glass ceramic tiles have been completely fitted. The service room of the pool is built. The granite, exterior tiles on the patio around the pool have also been fitted.
A concrete-contact primer was laid on the walls of the pool in Balchik. Laying of coping stone begins with leveling. Then the walls are plastered and rendered. Waterproofing strips are laid on corners, as well as two-component waterproofing on walls. The coping stone has been fitted. Then the glueing of the glass ceramic pool tiles and the grouting begin.
The patio around the pool is prepared for the concrete - gravel has been compacted, then rebars are fitted, shuttering is also ready. Then the concrete is poured.
Bituminous primer is applied on the outer walls of the pool. The skimmers and the pipes are installed. The electricity and water supply of the pool are also installed. Then soil is backfilled.
The double-sided shuttering on the walls of the pool is completed. The reinforcement at the bottom of the pool and the piping are installed. The skimmers are mounted. We pour the concrete on the walls and bottom of the pool at the same time. Then we vibrate the concrete to spread evenly. Then it is leveled by hand and machine for an even and smooth surface. Bituminous primer is applied on the outer walls of the pool. The shuttering of the service room is unmounted.
The shuttering of the pool's walls is fitted. The levels are determined. Then the reinforcement is installed. The workers are fitting the piping.
The construction of the pool in Balchik begins with excavation works. Then the foundation concrete is poured.