Construction and repair works of swimming pool in Varna.
Building company Varaks managed to do the following building works of this swimming pool in Varna:
- Reconstruction works - removal of exterior tiles, demolish of concrete flooring, excavate trenches, demolish walls for fitting of skimmers, double shuttering for service room, rebar, pour and carry concrete by hand, supply and fit iron lid for the service room, new drainage pipe for floor siphon, backfill soil and compact, fit membrane before concrete, rebar, concrete, floor screeding, supply and fit exterior tiles.
- Pump, filter system and equipment - supply and fit skimmers, pipes, fittings, brackets, valves, automatic water filling system, nozzles, pool pump, filter with mixed quartz sand, electricity system, wiring, electricity panel, fuses.
- Pool tiles and stones repair - demolish old ceramic pool tiles of the steps, screeding and shaping the steps, waterproofing insulation, supply and fit new ceramic tiles, repair of small and large pools' walls and bottoms, clean and grout pool border stone.
- Tiles around the pool - unmount old tiles, floor screeding (concrete, rebars, shuttering), fit new exterior tiles.
The repair works on this pool near Varna are completed. The service room is done and the patio around the pool is also finished.
The granite tiles around the pool are completely fitted. The border stone has also been fitted and is to be jointed. The lid of the service room is ready. Repairs are underway on the steps inside the pool, as well as on the entire perimeter of the upper part of the glass ceramics.
The tiles around the pool are almost fitted, with the fugue in progress. The board stones are being fitted.
Next the membrane before concrete is installed. Then the rebar is fitted an we start pouring the concrete. We then start fitting the tiles.
The backfill around the pool is ready. The new skimmers and nozzles are fitted. The pipes are also installed.
The trench around the pool is ready. The service room is also completed. The workers now mount the skimmers, the nozzles and the pipes. New power cable is installed.
Excavation works around the pool continue in order to allow sufficient depth to fit the pipes. The place for the new service room with a depth of 2 m is also dug. The walls of the pool where skimmers and nozzles will be installed have been demolished. The border stone is unmounted. Initial concrete base for the service room is being laid. The concrete is then poured with mixer pump.
The works continue with excavate trenches 1х1 m and remove earth by hand on distance of 46 m. We will then fit the pipe installation there.
This project near Varna begins with taking the measures for the required works. The exterior tiles are then removed and the demolish of concrete flooring is demolished with width 1m.