The construction works on this property in the village of Petrov dol, near Varna, include:
- Garage - leveling cement screed, brick masonry, supply and lay concrete-contact primer, cement screed with slope;
- Increasing the level of the patio in front of the house - supply, carry and spread gravel;
- Rear wall of the garage (retaining wall) - one-sided shuttering, excavation of foundations by hand, reinforcement of foundations and wall, supply and pour concrete in foundations and retaining wall;
- Concrete path at the back and sides of the garage - leveling the terrain, formwork, supply and fit polyethylene membrane and rebars, supply and pour of concrete class B-25;
- Concrete ramp - manual excavation, removal of earth masses with wheelbarrows at a distance of up to 50 m, level and compact ground, fit polyethylene foil and reinforcement, concrete, formwork;
- Concrete patio in front of the house - cleaning the site, shuttering, laying reinforced concrete;
- Path from the house to the garage - level the terrain, shuttering, supply and fit concrete-grass and curbs;
- Wall beside the driveway and driveway - excavation for concrete support of the hanging wall, supply and fit reinforcement, supply and fit shuttering, supply and pour concrete.
The screed in the garage is laid, as well as the screed on the roof of the garage. The concrete board of the garage is also done.The workers are coating the walls of the garage and are making a path of grass concrete.
The masonry of the outer walls of the garage begins. Formwork is made on the concrete board around the roof of the garage. The shuttering and reinforcement of the retaining walls in the yard and the ramp are ready. The storage of the house is cleared and the floor there is prepared for pouring concrete. The workers pour concrete on the concrete board of the garage, the retaining walls and the ramp in the yard. They are ready with the masonry of one garage. Concrete is being poured into the storage room, and the concrete on the ramp in front of the yard is ready.
The one-sided formwork was made on the back wall of the garage, after which the concrete was poured there. Polyethylene foil and reinforcement are laid for the concrete ramp and concrete patio in front of the house. Then concrete for the patio, paths and ramp was poured. The trench for concrete support of the hanging wall to the gate is ready. Reinforcement for the fence has been fitted.
Gravel is laid and the levels are determined before laying the concrete on the patio in front of the house. The old steps are demolished. The trench for the ramp is dug. The foundation for the retaining wall behind the garage is made and the reinforcement is laid there. The excavation, shuttering and reinforcement of the concrete path around the garage are ready. The workers are demolishing and digging for the new concrete ramp from the street to the garage. Excavation works on the retaining wall around the garden are in progress. Water and sewer pipes have been laid and a tap has been built outside.
The construction works of the house in Petrov dol are starting. An excavation is being made for foundations at the back of the garage. The earth masses are removed by hand with a wheelbarrow. The site in front of the house is being cleaned.