The works on this project in Balchik include:
- Construction of a scaffolding ramp;
- Clearing of earth masses;
- Demolition of old retaining walls and demolition of an old foundation of a retaining wall;
- Construction of new retaining walls.
The work on the construction of the retaining walls and the concrete patio has been completed.
The shurreting is removed and a backfill is done. The wall in front is completed. The place in front of the retaining walls is reinforced and concrete is poured with a concrete mixer. The scaffolding has been dismantled.
The reinforcement for the retaining walls is fitted, as well as the shuttering for the retaining walls. The shuttering is fitted and the reinforcement is installed for the steps, as well. The shuttering is fitted and concrete is poured with a stationary concrete pump for retaining walls, fences and staircase. Then concrete is vibrated. After a couple of days the shuttering is removed.
An excavation by hand is made for the foundations of the retaining walls. Then reinforcement and formwork are fitted. Concrete is poured with a stationary concrete pump for the foundations of the retaining walls.
The works in Balchik begin with the construction of a scaffolding ramp, clearing earth, preparation for demolition of old retaining walls and demolition of an old foundation of a retaining wall.