The construction works in this property near Balchik include:
- Dismantling of front boards and old guttering system. Delivery and installation of new ones;
- Demolish brick masonry;
- Delivery, installation and dismantling of scaffold;
- Delivery and installation of thermal insulation on walls;
- Plastering with mesh, delivery and laying primer and mineral plaster;
- Fit skirting;
- Rough construction of the bathroom - excavation of foundations, formwork, reinforcement, concrete, brickwork, plaster outside and inside, roof over the new part, removal of old tiles, electrical equipment and plumbing;
- Loading and removal of construction waste;
- New tiles and bathroom equipment.
The bathroom works have finished. The tiles are fitted and grouted. Sink, toilet unit and boiler are also fitted. New shower cabin is mounted.
The tiling works and finish of the shower room continue in May 2020 - on the second phase of the repair works.
The facade is finished and the rough construction of the bathroom also.
The mineral plaster of the house is finished. The workers remove the rubbish out of the site. The lighting in the bathroom and the facade switch are mounted. Then the skirting arounf the house is fitted. The bathroom window and the door to the under roof room are mounted. The concrete patio is also completed.
The fascia boards are varnished and mounted. Then the corners will be plastered. The heat insulation is installed. Then we will repair and plaster around the new doors and windows. Then the plaster is laid and we primer before laying the mineral plaster.
The plumbing and the electrical installations are ready. In the bathroom, the plasterboard is plastered. Then the fascia boards are fitted. We changed the pipes in the water shaft. The concrete around the bathroom is poured.
The works begin with the rough construction of the bathroom. The plumbing and the electrical installations are being installed. The site is cleared. We prepared the base and the concrete is poured.
The house near Balchik and its state before the renovation began.