After the renovation of the facade of this administrative building in Balchik, we begin to repair the inner part of the building. The repair works include: dismantling works, demolish plaster and flooring, delivery and laying of primer concrete contact, cement reinforced flooring, two-component waterproofing, fiberglass 3 cm on the walls, plaster, priming and painting. An internal staircase and the space between the staircase will also be repaired. A bathroom will be built and switches, sockets and lighting will be installed.
The works on the administrative building in Balchik are completed. The partition walls are built. The concrete beams and columns are boxed in plasterboard. The concrete bed is finished. The works on the el.installation are also completed. The fine plaster is laid.
The works are going to an end. The patio in front of the building is completed. The floor screeds are in progress. The works on the walls continue.
The patio in front of the building is almost ready. We box in the columns with plasterboard. Plastering works are also almost finished.
The render of the walls and the floor screedings are ready. The metal frame of the door is fitted. We continue with plastering walls and drilling floor for drainage. The concrete driveway to the garage is finished. We fit the stone on the patio in front of the building. The heat and waterproofing insulation on the staircase is on the go.
UPVC windows are mounted. We repair and plaster around the new windows. In some of the rooms the render is completed. In others it's already plastered and the painting will start. We removed the old damaged render from staircase and prepare for plastering. The concrete for the way to the garage is poured.
The render is almost finished, then we plaster and new windows are installed. In the course of the works, some additional work is fulfilled. Outside, a plumbing breakdown has been fixed and the outside pavement will be fitted.
The plastering begins. The walls and floor are partially demolished in order to locate the leak and make the drainage. The bathroom is on a rough construction stage. Plastering continues.
The demolition works inside continue. The opening for the door is ready. We have prepared the tracks for the bathroom drainage. The drainage works for the groundwater also continue. The pipes and the linear drain are installed.
The repair works in Balchik start with demolition of the floor inside the building where the new drainage pipe will be installed. A trench for the underground water line is dug outside. The pipes are then installed and supported with concrete rings.
This is the condition of the building inside before the renovation starts. The walls are badly damaged, the staircase and the area there needs repair. The pipe system will be re-done and new shower room built.