The building works in this house in village of Dubrava continue with making a new floor screeding. The works include: supply and fit of floor insulation (the insulation sheets are 3 cm thick), supply and fit reinforcement bars (5 x 5 cm) and supply and pour concrete (up to 5 cm).
These works are part of a bigger project of installation of underfloor heating in the house.
The building works in Dubrava have finished with the installation of the screeding. The floor in each room is completed and ready for further steps regarding the repair works.
After the fiber and the reinforcement have been installed in all the rooms, it's time to pour the concrete on top. The concrete is prepared on spot and laid all by hand.
The materials are delivered to the building site. First step is to lay the insulation. The fibеr sheets are with 3 cm thickness. After that the reinforcement grid with size 5 x 5 cm is installed.