Construction company Varaks has competed the rough construction of a new extension in this school in Dobrich. At the beginning of the construction works, preparatory and dismantling works were done, including assemble of scaffolding and fitting of a mobile fence. The existing concrete pavement, a passage, including walls and concrete, and steps were demolished, and the waste was transported to a depot. A mechanized excavation was done for the new foundations and the excavation was shaped by hand and compacted. Gravel was spread under the pavements.
The professional building workers of building company Varaks have completed all the shuttering, reinforcement and concrete works - including a foundation slab, walls, columns, beams, slabs and a staircase. Part of the structure was built at a height of 4.05 m, with the slab forming a shed. Underlayment concrete and structural concrete were poured with a concrete pump.
Reinforcement grids and reinforcement bars were fitted. Masonry was completed with solid bricks of various thicknesses. XPS thermal insulation was fitted under the flooring, on the foundations and on the flat roof. Two-component waterproofing was laid on the walls, the foundation slab was also waterproofed, as well as a complete waterproofing of the roof - primer, adhesive, gas-fired waterproofing.
Old plasterboard structures were dismantled and the building rubbish was loaded and transported. External site works have also been done - filling and compact gravel, as well as the building of a concrete sidewalk around the new part. All construction works have been done in accordance with the project and building standards.
Construction company Varaks began building work of this school in Dobrich by demolishing the existing pavement and steps, after which the building rubbish was transported from the site. A mobile fence was installed to secure the construction area. Mechanized excavation for the new foundations was done, followed by shaping by hand and compacting of the base. Gravel was spread and compacted under the future base. Formwork and reinforcement works begin, including pouring of underlay concrete. Construction of the new extension to this school in Dobrich is starting very well. The photos show the progress of the preparatory and constructive building works.