The construction works of the garage in Balchik include:
- Dismantling works - dismantling of ridge tiles and roof tiles, dismantling of a double grid on a roof, dismantling of a suspended ceiling of rotten beams and boards, dismantling of under-roof foil and cleaning, dismantling of rotten boarding and battens partially of the roof, manual loading on truck or trailer, supply, assemble and disassemble scaffolding.
- Mounting works - impregnation of timber, reinforcement of the roof of the workshop, installation of additional beams, installation of a ridge beam, installation of joists and trusses, cleaning of wooden boarding, apply bituminous primer, apply bituminous foil, installation of bituminous panels, impregnation of OSB boards and installation of internal joists, cement plaster with a thickness of more than 3 cm at a height of more than 3 m, installation of spouts, installation of galvanized gutters and brackets, installation of fascia, impregnation and varnishing.
The building works on the site in Balchik have been completed. The roof of the garage is done. The OSB boards are fitted. The interior works have also been completed.
The laying of insulation on the roof continues. The fascia and the OSB boards are primed and varnished. After the insulation is laid, the installation of corrugated bitumen sheets begins. The internal joists and the OSB boards are fitted.
The building works on this site begin with the dismantling works. The workers load the building rubbish and transport it. Then the roof is reinforced. Wooden battens are fitted and OSB boards are installed. The boards are primed with a bituminous primer and a waterproof membrane is installled on them. The walls around the roof are plastered.