Lots of building and repair works have been implemented in this mill during the summer of 2019. The building and repair works include: unmount pipes, supply and fit new dranage pipes for fireplugs, repair of water and plumbing installation, demolish flooring, patch tile flooring, supply and fit tiles in the laboratory, meeting room, offices, fit industrial purposes sinks.
The tiles in the laboratory, the meeting room and the offices are fitted. The water and fire systems are ready. The industrial purposes sinks are also fitted.
The works on the water supply and sewerage system continue. The floor screeding is laid in preparation for laying the tiles. The fire valves are installed in the warehouse. New openings have been drilled. Tiles fitting and the fitting of the moulding is in progress.
The works begin with demolition of the existing floor surface. Then the water lines for the fire cocks are built. The flooring repair begins.