The owners of this house in Balchik contacted construction company Varaks about the finishing works on their villa by the sea. From the very beginning, mutual trust and understanding was established between our team and the property owners, which made the work on the site easy, organized and stress-free.
Our building workers done a number of construction and installation works on the site, which included:
- Brickwork for bathrooms on the ground and first floor;
- Internal plastering on walls and ceilings (ground and first floor, bathrooms and bedrooms) - applying contact primer, plastering walls and ceilings;
- Screeding inside the house and on the veranda - applying contact primer, floor screeding;
- Screeding for the paths around the house - applying contact primer, floor screeding;
- Concrete boards under UPVC doors (ground and first floor) - making a base for the door frame, shuttering, reinforcement and pour concrete, removal of shuttering;
- Concrete patio and steps at the entrance door (first floor) - formwork for steps and patio, reinforcement and pour concrete, strengthening with supports, formwork removal;
- Facade and balconies - supply, assemble and disassemble scaffolding, lay contact primer, plaster the facade walls, fit insulation, supply and fit fibermesh, primer, apply mineral render;
- Supply and fit mineral wool between the rafters of the ceiling on the first floor;
- Decorative roofs on the first floor balcony – supply and fit wood, wooden boarding, waterproof membrane, roof tiles, ridge tiles and fascia;
- El. installation and lightning protection - install and connect the main switchboard and boiler switchboard, installation of switches, sockets and consoles, mount different types of cable, supply and fit pipe and grounding, supply and fit lightning rod, conductor, connector and grounding rod;
- Plumbing installation - complete installation of a plumbing system in the house.
Building a house in Balchik
The construction works of this house in Balchik continues with precise plastering of the interior walls and ceilings. The new bathroom is fully built and plastered. Our construction specialists prepared the facade walls with contact primer and applied external plaster with these activities being done at a high height in compliance with all the safety standards. After the render has been applied, the team of construction company Varaks begins the installation of the plumbing system in the house.
Building a house in Balchik
Construction company Varaks began construction and installation works on this house in Balchik with the fitting of the electrical installation of the house. Our building workers cleaned and prepared the site before the building works began. Then, experienced electricians installed cables in all rooms.
At this stage of the construction of the house the YTONG doorsteps under the UPVC doors have been removed and new ones have been made of reinforced concrete. A concrete platform and steps to the entrance door have been poured and reinforcement has been made with support beams at high altitude. The masons started shaping the walls of the bathroom. In parallel, the UPVC windows and doors were covered with dust sheets and scaffolding has been built for the upcoming works on the facade.