The building site is located in Varna, near the sea. The project includes 210 sq.m. total internal area of the house. The ground floor will comprise of open-plan kitchen with living room as well as shower room storage room. The first floor will have 3 bedrooms and 2 bathrooms.
Outdoor area will offer big garden and parking lots.
The building works in May continued with making shuttering, fit reinforcement bars and laying concrete of the first floor concrete plate, make suttering and fit reinforcement bars of the retatining concrete wall and columns of the first floor.
Due fo the difficult access to the building site, the builders cannot use concrete mixer pump but only stationary one. To do this, a scaffolding had to be assembled in order to work with the pump.
The building works continue with brick masonry on the ground floor, shuttering, reinforcement and concrete works of the north side concrete wall of the house, laying concrete, shuttering and concrete works of the first floor concrete plate.
The waterproof and heat insulations of the retaining wall behind the house are also done.
The construction works of this house in Varna are well organised and are on schedule. In March, the workers and technicians of Varaks building company managed to complete the works up to level +3,20m. Water and sewarage system works are also done in level 0. Prior to fitting the shuttering all the shuterring forms were treated with special oil. Due to the narrow street and difficult access to the building site we had to use telescopic wheel loader and stationary concrete pump in order to pour concrete into foundations, concrete plate, columns and concrete walls. Vibration of the concrete was done at concrete pouring. After pouring the concrete, it was treated and polished. The construction works continue with assembling of scafolding. The first layer of bituminous primer was laid onto the supporting wall behind the house.
After a short stop of the works because of bad weather condition the construction works of this house in Varna continue with excavation for foundations. Varaks construction company's technicians give the exact levels of the depth of foundations and contours/perimeter of the house are outlined and marked.
Supply and put gravel and then backfil before we pour the first layer of concrete.
Due to the very restricted and narrow access to the building site we cannot use concrete pumps and lorries.
At this stage we use mini excavator to get concrete from the concrete mixer and carry and pour it.
All the reinforcement bars are carried by hand to the building site too.
The reinforcement fitting works are done and we are ready to pour concrete in the foundations.
The construction works of the house in Varna commence with landscaping the area in order to give enough space for excavation of foundations.