Varaks Construction company has successfully completed another project at a photovoltaic power plant near Dobrich. The project involved construction works for reinforced concrete ramps, stabilisation of the adjacent road section and site drainage.
Mechanical and manual excavation works were carried out, followed by the formation of the design levels and preparation of the ground through leveling and compaction. A crushed concrete sub-base was installed to provide a stable and reliable foundation for the subsequent building works.
A key element of the project was the construction of the ramp’s reinforced concrete structure. The works included formwork for strip beams, installation of reinforcement, pouring of blinding concrete and construction of a reinforced concrete slab. Concrete mixes were selected to suit the specific requirements of each structural element. Movement joints were also installed.
The project also included stabilisation of the adjacent road section using mass concrete with large stone aggregate. Following preparation and compaction of the ground, layers of crushed stone and recycled geotextile were laid, followed by mass concrete incorporating large stones. This solution helps minimise the risk of erosion and ground movement.
The completed project provides a functional infrastructure base, combining the strength of the reinforced concrete structure with reliable stabilisation of the surrounding terrain. Each stage involved complex construction and installation works requiring a high degree of technical precision, specialist expertise and strict adherence to established construction methods.
During the initial phase of the project, Varaks Construction company carried out preparatory works for the construction of ramps serving the photovoltaic power plant in the Dobrich area. The work began with mechanical and manual excavation, formation of the design levels and preparation of the ground. This was followed by the installation of polyethylene sheeting and double-layer reinforcement mesh.
At this stage, the pouring of base concrete began on one of the ramps. The concrete was delivered by mixers and poured using a concrete pump, with the Varaks team carrying out the concrete placement and initial levelling.