Varaks Construction Company completed the construction and installation works for the foundations of a new photovoltaic power plant near Dobrich. The project included the following construction activities:
The construction of the foundations for a photovoltaic power plant near Dobrich is progressing according to plan. At this stage, the base concrete has been poured and the layout works have been completed. The formwork was installed and the reinforcement for the foundation slab was fitted, after which the concrete for it has been poured.
Subsequently, the team of construction company Varaks completed the shuttering and reinforcement of the reinforced concrete walls to an elevation of ±0.00. Pipes with diameters of Ø160 and Ø200 were pre-installed within the walls to form openings for cable routes. Upon completion of the formwork and reinforcement works, the walls were concreted.
Building company Varaks began the construction of the foundations of a photovoltaic power plant near Dobrich by carrying out site layout marking. Following the surveying and staking-out works and the installation of batter boards, a mechanized excavation for the foundations was done.
Due to the excavation depth, the layout marking process was carried out in two stages. Initially, the upper excavation boundary was marked out, after which an additional layout marking was performed at the next level until the elevation specified in the project was reached.
This approach resulted in a double layout marking process, ensuring the required accuracy in the execution of the excavation works.